Train services through Florence have returned to normal following the completion of the first phase of works to replace the Ponte al Pino railway overpass.
Rail traffic resumed as scheduled on Friday, July 10, on the Firenze Campo di Marte–Firenze Rifredi and Firenze Campo di Marte– Firenze Santa Maria Novella lines after the conclusion of the initial construction window led by Rete Ferroviaria Italiana (RFI), part of the Ferrovie dello Stato (FS) Group.
During the rail closure, engineers completed the removal of the old bridge deck using a 2,000-tonne crane, one of the largest cranes deployed for this type of operation in Europe. Demolition also began on the existing bridge abutments, paving the way for the installation of the new structure.
Carried out in one of Florence’s most densely built-up areas, the project is considered one of the most technically complex engineering operations currently underway on Italy’s national rail network. Around 70 highly specialized workers from leading construction and heavy-lifting companies were involved in the operation.
The temporary traffic measures introduced to accommodate the works have now been lifted. Restrictions in via Mannelli, viale Mazzini, via Masaccio, piazzale Montelungo and via del Pratellino have ended, while the pedestrian footbridge and via degli Artisti, between piazza Vasari and via Masaccio, reopened earlier this week.
The second and final construction phase is scheduled to take place from 11pm on Sunday, July 26, until 11am on Thursday, July 30 with similarly affected rail and local transportation services. During this period, crews will install the new railway overpass, a structure weighing approximately 550 tonnes, marking the final major milestone in the Ponte al Pino replacement project.